$3 million Contract to Resurface Portions of S.R. 62 in Jefferson County

The $3 million contract was awarded in July 2020 and is expected to be complete by August 31.

INDOT Photo.

(Jefferson County, Ind.) – The Indiana Department of Transportation contractor MAC Construction plans to begin work on or after Monday, April 12.

Crews will be patching, milling, and repaving two sections of State Road 62 in Jefferson County.

Crews will begin with patching between the east junction of State Road 56, east of Hanover, and the bridge over Big Clifty Creek near Clifty Falls State Park. Daytime closures will be in place while work is in progress.

Later this spring, crews will move to the second section of State Road 62 from U.S. 421 to the west junction of State Road 250.

The $3 million contract was awarded in July 2020 and is expected to be complete by August 31, 2021. Motorists are reminded to slow down, use extra caution, and drive distraction-free in and near all work zones. All work is weather-dependent and schedules are subject to change.

More from Local News

Events

Local News

Trimble Co. Man With Child Sexual Exploitation Offenses

Undercover investigation led to the arrest

Taxpayers Not Required to Pay for Inmate Gender Surgeries in Kentucky

The Attorney General rejected the assertion that taxpayers would have to pay for the surgeries

Indiana Attorney General Todd Rokita files six lawsuits on behalf of buyers

Driving away deceptive conduct in the used car industry

Local Sports

Local Sports for December 20,2024

Any missing scores or to report a score email news@953wiki.com

Local Sports for December 19,2024

Any missing scores or to report a score email news@953wiki.com

ORVC Weekly Report Summary (December 9 – 14) 2024

Congratulations to all the area athletes